Attendees listen to a Michigan Department of Transportation representative talk about the Fort Street north of Van Horn Road railroad crossing improvement study July 15 at the Westfield Community Center in Trenton.
By SUE SUCHYTA
Sunday Times Newspapers
TRENTON – Representatives from the Michigan Department of Transportation provided an update July 15 on the proposed railroad overpass on Fort Street north of Van Horn Road at the Westfield Community Center.
MDOT’s engineering study and environmental review considered three options: building a bridge over the Canadian National crossing, going under the railroad crossing, and keeping the intersection as it is at present.
Currently, MDOT is doing an environmental and pedestrian access review, a topographic survey, a geotechnical investigation, and is looking at the utility coordination.
In addition, MDOT is doing a stormwater, noise and crash analysis, is reviewing railroad operations and is preparing cost estimates.
A third open house will be held in late 2026 or early 2027, with the design phase running through 2028 and construction occurring from 2029 to 2030.
At present, there are about four train crossings from 6 a.m. to 6 p.m., and another four from 6 p.m. to 6 a.m., with each train crossing lasting two to three minutes.
From Jan. 1, 2020, to Dec. 31, 2024, 138 crashes have occurred near the M-85 Fort Street and Van Horn Road intersection or on southbound Fort Street between Marian and Norwood drives, north of the railroad crossing. It is hoped that an overpass would improve overall corridor safety.
Going under the railroad crossing does not address flood mitigation issues, and would require a pump station and permanent dewatering, with a levee required to address floodplain issues.
Bedrock removal would require careful attention to carbon monoxide and methane gas deposits, and the presence of hydrogen sulfide.
The crossing is also close to the Frank and Poet Drain, a local tributary that runs from Detroit Metropolitan Airport through the city of Trenton to the Detroit River.
Doing nothing would not address floodplain issues nor the delayed response time for emergency vehicles and school buses.
MDOT Project Manager Jeff Horne said the funding for the project is secure, and it will be four years until the overpass is completed.
Horne said the potential for flooding and the location of the Frank and Poet Drain are key reasons why a decision was not made to go under the railroad crossing.
“If you have a 100-year flood, it would essentially crest over onto M-85 and we would have no way of pumping that water anywhere to open the travel lanes,” he said. “Basically, Frank and Poet Drain would flood on M-85, the pump station would go, but really it would pump into an already crested drain, so it would be a continuous cycle that would not help or alleviate the M-85 project.”
Horne said when construction begins, Fort Street will have one lane of travel in each direction instead of the two it currently has.
“There will be an impact to motorists for roughly two years, but we are not going to fully close it,” he said. “The roadway – M-85 – will stay open.”

A Michigan Department of Transportation rendering shows the preferred proposal to overpass the railroad crossing on Fort Street north of Van Horn Road during a community presentation July 15 at the Westfield Community Center in Trenton.
Horne said official detours have not yet been developed, but MDOT will try to avoid county and local roads in any planned detour, and it is possible that an official detour may not be assigned since the road will not be closed during construction.
He said blasting of the bedrock during construction will not be an option because of the presence of methane gas.
“You will have to do controlled removals,” Horne said. “We do geotechnical analysis, look at the ground, look at water tables, look at gases and the type of soil – is it bedrock – things like that.”
He said the closer one gets to the Detroit River, the closer the bedrock is to the surface. It is about 15 feet from the surface at the railroad crossing.
Horne said he would encourage residents to be patient with MDOT during the construction phase of the project.
“We are working towards an alternative here and a concept and a project here to alleviate the congestion and to make it safer for motorists,” he said. “The safety aspect is very key, in addition to mobility, and we want police, fire and buses to and from the hospital, Corewell Health, a level 2 trauma center, so we want good access that is reliable, and the last thing we want is a patient in the back of an EMS truck to get held up by a train.”
Horne said the overpass will be designed to take any sort of load that is currently allowable in Michigan.
The study is available online at Michigan.gov/MDOT/projects-studies/studies/M-85-railroad-crossing-study.
Questions may be directed to Jeff Horne, project manager and professional engineer, at [email protected].